Delivery 5 min read

How Does Delivery and Installation Work?

Transport, crane positioning, and assembly process for modular timber homes explained step by step.

Quick Answer: Modular homes are transported on low-loader trucks and lifted onto the prepared foundation by mobile crane. The actual installation takes 1-3 days.

From Factory to Installation

1

Factory Production

Modules are fully manufactured in the factory: walls, floor, ceiling, windows, electrical, plumbing — all installed in controlled conditions.

2

Transport

Finished modules are weather-protected, wrapped, and loaded onto special transport vehicles. Long-distance transports often travel at night.

3

Crane Positioning

A mobile crane lifts each module from the truck and places it on the foundation. This takes approximately 30-60 minutes per module.

4

Module Connection

Modules are connected to each other, joints sealed, roof completed. Typical duration: 1-2 days.

5

Final Connections

Electricians and plumbers connect internal systems to the foundation utilities. Testing and commissioning.

Site Requirements

Access Road

  • Width: Minimum 3.5 meters, preferably 4 meters
  • Turning radius: Minimum 12 meters outer radius
  • Load capacity: 40 tonnes (heavy transport)
  • Height: No obstacles under 4.5 meters (power lines!)

Crane Standing Area

The mobile crane needs a firm, level surface near the foundation:

  • Standing area: approximately 8 × 10 meters
  • Load-bearing for 60-100 tonnes (crane + load)
  • Distance to foundation: max 15-25 meters (depending on crane configuration)

Foundation

The foundation must be complete and cured before delivery. For concrete: minimum 28 days curing time. Dimensional tolerance: max ±5mm.

Transport Dimensions and Weights

Parameter Standard With Special Permit
Maximum width 3.0 m 4.5 m (up to 5.0 m)
Maximum length 12.0 m 16.5 m
Maximum height 4.0 m 4.5 m
Weight per module 8-15 tonnes (depending on size and fit-out)

Transport and Installation Costs

Typical costs for a 2-3 module project:

  • Transport: €3,000 – €8,000 (depending on distance)
  • Crane: €1,500 – €3,000 (daily rate plus mobilization)
  • Installation team: €2,000 – €5,000 (connection and sealing)
  • Final connections: €2,000 – €5,000 (electrical, plumbing)

Total: approximately €8,000 – €20,000 for transport and installation.

Check Delivery Feasibility

Share your location and we'll assess accessibility and provide delivery cost estimates.

Start Location Check

Frequently Asked Questions

How are modular homes transported?

Modules are transported on low-loader trucks or special transport vehicles. Maximum width is typically 4-4.5 meters (with permits up to 5m). Larger homes consist of multiple modules.

How long does installation take?

The actual installation (lifting and connecting modules) takes 1-3 days. Connection work (electrical, plumbing, finishing) adds 1-2 weeks.

Do I need a crane?

Yes, a mobile crane is required to lift modules from the truck and position them on the foundation. A typical residential module weighs 8-15 tonnes. Crane costs: approximately €1,500-3,000 per day.

What site access do I need?

Access road should be at least 3.5m wide with 40-tonne load capacity. The crane needs a level standing area with solid ground near the foundation.

What needs to be ready before delivery?

Foundation must be complete and cured. Utility connections (electricity, water, sewer) should be at the foundation. Access road must be clear and load-bearing.